Overview of revised design and estimate of
Kamarpara RPWSS under Bangladesh Rural Water Supply & Sanitation Project.
Kamarpara Rural Piped Water
Supply Scheme, Jhikargacha Upazila, Jessore district was proposed to consist of
three villages namely Kamarpara, Fatepur and Jafarnagar village under
feasibility study (BETs) . But considering technical and financial point of
view as per report submitted by the team (PMU team including technical
consultant of WB visited the site), Kamarpara (288 HHs) village has not been considered
for implementation of the scheme and decision has been taken to implement the
proposed scheme in the two villages (Fatepur -366 HHs) and Jafarnagar- 466 HHs)
instead of three villages.
Total households in Fatepur
and Jafarnagar village are 832. But during preparation of road net work map for
designing the distribution pipe line for the scheme, only 641 number households
are found technically feasible to connect under this distribution net work.
Remaining 191 number households are located in scattered area and far away
(some cases there are no road to reach) from the distribution net work. So, these 641 number households are
considered as potential for the scheme. But as per previous experience and
field visit report, it is revealed that maximum 70% of these existing households
would take the house connection from the scheme in the first year of operation.
So, 450 numbers (70%) house connection are included in the estimate of the
scheme. Remaining connections would be done gradually in the following years of
operation of the scheme. But, for design purpose projected population based on the
existing 641 households are considered.
Calculation
of water demand
Present HHs = 641 nos. Population per HH (assume) = 5 nos. Present populations = 3205 nos.
Considering population
growth rate of 1.4% and 20 years project period, projected populations = 4232
nos. (Equivalent to 846 HHs)
Present water demand per day
= 3205x65x1.15=239573.75 liters (Assume LPCD=65 liters, L&W=15%)
Projected (20years) water
demand per day = 4232x65x1.15=316342.00 liters
Supply
Hours
Considering availability of
electricity, intermittent water supply in the scheme would be feasible. Total
supply of water is considered 8 hours in a day (3+3+2).
Design
of Over Head Tank
Capacity of the Over Head
Tank has been considered 1/3 of the projected water demand in a day which would
be very much adequate for the scheme.
Soil investigation report
provided by the consultant has been followed during designing of the foundation
of OHT. But, for technical reliability and soundness of the structure another
soil investigation has been kept in the estimate of OHT. Before construction,
soil investigation of the selected site would be carried out and based on the
soil report foundation of OHT will be re-designed if required.
Production
Well design
As per bore log and design
provided by the consultant, production well has been designed. But, installation
of another test tube well (TTW) has been kept in the estimate of the scheme to
explore and know the actual sub surface formation of the site. Based on the
report of TTW, final design of production well including pump will be done and
accordingly will be installed.
Distribution
Pipeline Network
Distribution pipe line
network has been designed considering the projected water demand of the scheme.
Other components such as
pump house, boundary wall, power supply, land development etc. have been
designed as per requirement of the scheme.
The cost (capital) for
different components of the scheme is shown in the following table.
SL
#
|
Description
of items
|
Quantity
|
Unit
|
Cost
in Taka
|
|
1
|
38 mm dia. Test Tube Well (300 meter depth)
|
1
|
No.
|
60,490.00
|
|
2
|
200mmx150mm Production Well
|
2
|
No.
|
25,11,980.00
|
|
2
|
Submersible Pump
|
2
|
No.
|
10,78,364.00
|
|
3
|
Pump House including Office
|
1
|
No.
|
7,80,000.00
|
|
4
|
Over Head Tank (Capacity = 100 m3 )
|
1
|
No.
|
26,41,170.00
|
|
5
|
uPVC Distribution
Pipe Line including all relevant fittings
|
150 mm dia.(B class)
|
62
|
meter
|
37,42,682.00
|
100 mm dia. (B class)
|
1897
|
meter
|
|||
75 mm dia. (C class)
|
5409
|
meter
|
|||
6
|
House Connection
|
450
|
No.
|
18,00,000.00
|
|
7
|
Water Meter (wall mounted vertical type) including
meter box chamber
|
450
|
No.
|
22,50,000.00
|
|
8
|
Boundary Wall including one MS Gate of 4 ft x7 ft size (Double leaf)
|
60
|
meter
|
2,41,100.00
|
|
9
|
Electric
Connection (Electric poll, 3 phase transformer, energy meter, demand charge
circuit breaker etc.)
|
1
|
item
|
5,40,000.00
|
|
10
|
Land Development
|
1
|
item
|
10,00,000.00
|
|
|
Total capital cost=
|
1,66,55,686.00
|
|||
|
|||||
11
|
Social Development Officer for 18 months
|
15000.00/month
|
2,70,000.00
|
||
12
|
Formation of Community Based Organization
|
LS
|
30,000.00
|
||
|
Grand total=
|
1,69,55,686.00
|
Monthly
Operation and Maintenance cost (O&M)
Following minimum
cost (monthly) are considered to operate and maintain the scheme at sustainable
manner.
SL#
|
Area of O&M
cost
|
Unit
|
Nos.
|
Cost
/ month (TK.)
|
Amount
in Tk.
|
1
|
Scheme
Manager cum Accountant
|
Person
|
1
|
6,000.00
|
6,000.00
|
2
|
Pipeline
mechanic cum bill collector
|
Person
|
1
|
5,000.00
|
5,000.00
|
3
|
Pump
operator cum plumber
|
Person
|
1
|
5,000.00
|
5,000.00
|
4
|
Peon
/ MLSS
|
Person
|
1
|
3,000.00
|
3,000.00
|
5
|
Electricity
bill
|
LS
|
20,000.00
|
20,000.00
|
|
6
|
Repair
& maintenance including material and labour
|
LS
|
2,000.00
|
2,000.00
|
|
7
|
Testing
of water quality
|
LS
|
1500.00
|
1500.00
|
|
8
|
Transportation
|
LS
|
1000.00
|
1000.00
|
|
9
|
Stationeries
|
LS
|
1000.00
|
1000.00
|
|
10
|
Depreciation
|
LS
|
4,000.00
|
4,000.00
|
|
|
Total
cost per month =
|
48,500.00
|
Projection
of House Connection
Through out 20 years of project
period total number of house connections would be 841 nos. The scheme will be
operating with 450 house connection from the first year of operation. It is
assumed that within 10 years of operation 100% house holds would be connected
under the pipe line distribution network of the scheme. Tentative projection of house connection
during the project period is shown below.
|
Year of Operation
|
|||||||||
|
1
|
2
|
3
|
4
|
5
|
6
|
7
|
8
|
9
|
10
|
House
Connection
|
450
|
500
|
550
|
600
|
650
|
700
|
750
|
800
|
841
|
|
Assessment
of Community Contribution and Tariff Structure
A sample survey regarding
willingness to pay has been conducted by PMU team. Pattern of community
contribution as well as tariff has been analyzed and stated in the report which
is attached herewith for ready reference.